Model TSA 2006
Resolution By 
                                                                
                                                                        MoP                                                                
                                                                Effective Date 
                                                                
                                                                        The date when the Agreement is executed and delivered by the parties.                                                                
                                                                Term and Termination 
                                                                
                                                                        It shall automatically terminate unless extended by the Appropriate Commission.
The Agreement shall also terminate before expiry date as per some conditions.
[Clause 2.2]
                                                                The Agreement shall also terminate before expiry date as per some conditions.
[Clause 2.2]
Development of the Project 
                                                                
                                                                        -TSP's obligations in development of the project.
- Long term transmission customer's obligation in implementation of the project.
- Time for commencement and completion.
- Extension of Time.
- metering Arrangements.
                                                                - Long term transmission customer's obligation in implementation of the project.
- Time for commencement and completion.
- Extension of Time.
- metering Arrangements.
Construction of the Project 
                                                                
                                                                        - TSP's Construction responsibilities.
- Appointing contractors, Monthly progress reporting and supervision of work.
                                                                - Appointing contractors, Monthly progress reporting and supervision of work.
Operation and maintenance of the Project 
                                                                
                                                                        - Schedule and Unschedule outage.
- Responsibilities of various entities for operation and maintenance of the project.
                                                                - Responsibilities of various entities for operation and maintenance of the project.
Corrigendum/ Amendment, if any 
                                                                
                                                                        Yes                                                                
                                                                Amendment 1
                                                                        
                                                                
Resolution By 
                                                                MoP
                                                                
                                                                                                                                Amendment 2
                                                                        
                                                                
Resolution By 
                                                                MoP
                                                                
                                                                                                                                
Term and Termination 
                                                                Expiry date will be 35 years from scheduled COD instead of 25 years [clause 1.1.1, clause 2.3]
                                                                
                                                                                                                                Amendment 3
                                                                        
                                                                
Resolution By 
                                                                MoP
                                                                
                                                                                                                                
Development of the Project 
                                                                contract performance guarantee will be computed on the basis of ₹9 lakh/km for all lines and ₹0.75 lakh/MVA for substations instead of blanket ₹6 lakh/km [clause 3.3]
                                                                
                                                                                                                                
          